Contract EP-384.057
Amount: $10,252,868.00
Completed in 2007 this project expended Maher’s
Terminals Expressrail service by adding two additional tracks, # 9 and
10. The work included, railroad tracks, railroad mechanical works, complete
reconstruction of bituminous pavement, concrete pavement, major electrical
upgrades including site lighting, complete water main upgrade and major
underground and surface drainage installation.
|